Timeline
NEC compensation-event timeline.
NEC rewards procedural discipline and punishes drift. Map the key dates of a single compensation event — notification, quotation and the Project Manager’s reply — with the governing clause on each step and every period editable to your Contract Data.
cl. 61.3
cl. 62.3
cl. 62.3 / 64.1
The quotation and reply clocks run from the instruction to quote, not from notification. Fill this to date those steps.
- 1 Notify the compensation eventBy the deadline below · cl. 61.3 · default, overridable in Contract Data
- 2 Submit the quotationWithin the quotation period of being instructed to quote · cl. 62.3
- 3 Project Manager repliesWithin the reply period of the quotation · cl. 62.3 / 64.1
Enter the date the Contractor became aware to map the timeline.
The 8-week bar is not absolute. The clause 61.3 time-bar does not apply to a compensation event that arises from the Project Manager or Supervisor giving an instruction, changing a decision, or another Employer-side act the PM should have notified.
Indicative only, not legal advice. Default NEC periods are shown; your Contract Data governs the actual periods, and assessment also depends on the Accepted Programme. Periods are counted in calendar weeks. Always confirm against your contract and take advice on a live matter.