NEC compensation-event timeline.

NEC rewards procedural discipline and punishes drift. Map the key dates of a single compensation event — notification, quotation and the Project Manager’s reply — with the governing clause on each step and every period editable to your Contract Data.

cl. 61.3

cl. 62.3

cl. 62.3 / 64.1

The quotation and reply clocks run from the instruction to quote, not from notification. Fill this to date those steps.

Enter the date the Contractor became aware to map the timeline.

Indicative only, not legal advice. Default NEC periods are shown; your Contract Data governs the actual periods, and assessment also depends on the Accepted Programme. Periods are counted in calendar weeks. Always confirm against your contract and take advice on a live matter.